Industrial Wastewater Treatment and Reclamation Facility

  • Client:

    Confidential

  • Construction Value:

    Confidential

  • Delivery Method:

    Progressive Design-Build

  • Year Completed:

    In progress

  • Specialties:

    Manufacturing & Process Industries, Water & Wastewater

Features & Highlights

  • Immense project scale and aggressive 21-month schedule on mission-critical facility
  • Detailed metrics and dashboards kept all parties informed of planned vs. actual costs
  • Offsite manufacturing of key elements improved quality and schedule while reducing safety risks
Project Overview

Sundt built a new 12 MGD wastewater treatment and reclaim facility to treat industrial wastewater (IWW) for reuse for a large semiconductor manufacturer with zero liquid discharge onsite. The facility utilizes multiple treatment processes including chemical quenching of the IWW influent stream, biological nutrient removal (BNR), membrane bioreactor (MBR), biosolids dewatering treatment by screw presses, Hp reverse osmosis (HpRO) system, ion exchange system, concentrator and crystallizers, dewatering salt centrifuges, and multiple chemical systems to assist in the treatment processes.

The team took over the project from another design-build team following completion of the preliminary design. The project was significantly over budget and behind schedule, risking impacts to the client’s ongoing production. Our team identified the client’s project goals and the issues with the original design. The project’s aggressive 21-month schedule required several creative solutions, which included phased permitting and early procurement of long-lead equipment, as well as opening multiple work fronts concurrently to meet critical-path demands. Our team’s disciplined project controls systems allowed us to effectively manage the schedule.

The aggressive schedule meant the need for additional key administrative staff and skilled craft labor. In a short timeframe, our team staffed the project work to be done in double-shifts, six-day weeks for the majority of the project to finish ahead of schedule.

» Read More» Read Less

Market Leaders

 
Our team staffed the project with 60 administrative professionals and nearly 400 skilled craft labor professionals.

Link to Manufacturing and Processing Industries Video